Type Of Work | Lead time (In Days) | Remarks |
Knitting lead time | 10 | To be counted from opening yarn btb lc |
Knitting leadtime | 10 | To be counted from yarn inhouse date |
1st submission of lab dips | 7 | To be counted from receipt of colour standard |
Comments on 1st submission of lab dips | 7 | To be counted from receipt of lab dip |
Revised submission of lab dips | 5 | To be counted from receipt of lab dip rejection comment |
Comments on re-submission of lab dip | 7 | To be counted from receipt od lap dip |
Bulk hanger submission & pp fabrics | 15 | To be counted from lab dip approval date. |
Comments on first bulk | 7 | To be counted from receipt of bulk hunger |
Resubmission of bulk hanger & pp fabrics | 7 | To be counted from receipt of rejection comments. |
Comments on resubmission of bulk | 7 | To be counted from receipt of revised bulk hanger |
Lead time for dyeing completion of full qnty | 25 | To be counted from lab dip approval date. |
Fabric quality check at central store | 2 | To be counted from once fabric is inhouse at central store |
Important notes:
1) for any new quality of fabric, pls consider 2-4 weeks (depending on yarn availability) of fabric approval time.
2) The fabric dept will need to check and approve the shade of the first batch internally and go for dyeing of consequent batches. If they have confusion on shade matching/quality of first batch, then they should seek commercial approval to merchandising.
3) for grey material, yarn in-house to first bulk submission to be 15 days.